plain cement concrete 1 4 8 materials requirement for 1 cum

TENDER DOCUMENT VOL II (FINANCIAL BID) FOR DESIGN ...

Cum 4.00 4. 4Providing and laying plain Cement Concrete of 1:4:8 (1 Cement: 4 coarse sand: 8 graded stone aggregate 40 mm nominal size including form work and curing in foundation. Cum 1.00 5. 6Brick work with common burnt clay FPS bricks of class designation 7.5 in foundation and plinth in 1:6 cement mortar ( 1 Cement : 6 coarse sand) for ...

Different Grades Of Concrete | Based On IS, American ...

Normal grades of concrete. a. M5 Grade. Mixing Ratio is 1:5:10 ( 1 part of cement, 5 parts of sand and 10 parts of aggregate). Compressive strength is 5 MPa. Used in foundation bed to prevent direct contact between soil and foundation concrete. b. M7.5 Grade. Mixing Ratio is 1:4:8 ( 1 cement part: 4 sand part: 8 aggregate part).

Rates Analysis For Calculating Material and Labour for ...

Sep 13, 2014· Cement concrete 1:4:8 in foundations (a) Materials at site for 1 cu m payment per cu m Cement 3.41 bags @270 bag = 929.70 Sand 0.47 cu m @800.00 per cu m=376.00 21. Brick ballast 0.94 cu m @ 800.00 = 752.00 Cost of labour for 10 cu m = 7520.00 (b)Labour for 10 cu m Rs.

APPENDIX-I QUANTITIES OF MATERIALS FOR COMPLETED …

13 Cement concrete 1:1.5:3 cum Metal Cement Sand 0.82 cum 0.283 cum 0.41 cum 14 Cement concrete 1:2:4 cum Metal Cement Sand 0.85 cum 0.22 cum 0.43 cum 15 Cement concrete 1:3:6 cum Metal Cement Sand 0.90 cum 0.154 cum 0.45 cum 16 Cement concrete 1:4:8 cum Metal Cement Sand 0.92 cum 0.12 cum 0.46 cum 17 Cement concrete 1:5:8 cum Metal Cement Sand ...

How to Calculate Quantity of Material For Plaster? - Civil ...

Numbers of Cement Bags in 1 cum = 28.8 nos. How many Cft in 1 Cum = 35.31 cft. Calculation of quantity of material for 12 mm thick plaster of ratio 1: 6 (1 Cement:6 Sand) in the wall for 100 Sqm. The volume of mortar = Area × Thickness = 100 × 0.012 = 1.2

Financial Bid – PART- I BoQs (Annexure-1 ) SMART CITY ...

Cum 394 100-2 Plain Cement Concrete (1:4:8) (cement: fine aggregate: Coarse aggregate) for foundations and under flooring bed using coarse aggregate 40mm size hard, machine crushed granite from approved quarry including cost and conveyance of all materials like cement, sand, coarse

Computations of Quantities of Materials Required for ...

To determine the materials required for 1 cum. of (wet) concrete of 1:4:8 proportion, the dry volume of concrete required will be 1.52 cum. (which shrinks to 1 cum. after adding of water to it) As 1 cum. of cement is equivalent to 30 bags of cement (each bag weighing 50 kg) The quantity of cement required = 0.117 x 30 = 3.51 bags = 3.50 bags.

What is the difference between plain and reinforced concrete?

Sep 25, 2020· Concrete Ratio: Normally used proportions are 1:2:4, 1:3:6, 1:4:8. Unit: Cubic Meter (Cum) REINFORCED CEMENT CONCRETE (RCC) :-Concrete is material with a mix of Cement, Sand, Aggregate and Water, that is good for Compression not in Tension…. To resolve this critical issue by reinforcing steel, by casting wet concrete around strong steel bars.

PWD Tender - Name Of Work Widening And Improvements To ...

5117.8: cum-- ... more. 12.4 : Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically ...

M30 Grade of Concrete Mix Design Procedure with OPC 53 Cement

You can increase the cube numbers for three3 days, 7 days, or 28 days as per your requirement. Concrete Quantity Required for Trial Mix. Volume of 1 cube mould = 0.150 x 0.150 x 0.150 = 0.003375 cum. so concrete quantity for 1 cube = 0.003375 cum. concrete quantity for 12 cubes = 0.003375 x 12 = 0.0405 cum.

How to Calculate Cement, Sand and Aggregate required for 1 ...

Density of concrete = 2400 kg/cum. So, 1 bag of cement produces = 400/2400 = 0.167 cum. No. of bags required for 01 cum of concrete = 1/0.167 = 5.98 bags ~ 6 bags. From above, if the concrete mix is 1:2:4, to get a cubic meter of concrete we require. 1.Cement = 6 bags = 300 kgs. 2.Fine Aggregate = 115/0.167 = 689 kg

What is Plain Cement Concrete (PCC) in Construction of ...

Feb 07, 2019· A strength of PCC is defined as compressive strength after 28 days, expressed as M15, M20, where M stands for Mix and 15 stands for 15 N/mm 2 compressive strength at 28 days. The proportions of materials (cement, sand, coarse aggregate) for nominal mix/design mix concrete that are normally used are 1:3:6 or 1:4:8.

REF NO.CMC‐T210018 BILL OF QUANTITIES SCHEDULE ‐ A ...

Plain Cement concrete 1:4:8 using 40mm size HBG machine broken jelly,coarse Sand including mixing in mixer machine, laying, consolidation and curing etc. complete a 70.00 M3 For foundation and flooring 1M3 10 Supplying, fixing and removing ofsteel centering and shuttering to correct line and levels fully leak

Plain cement concrete (PCC)- Materials, Properties, and Mixing

The ratio of materials in PCC: The ratio of cement, sand, and brick chips in the foundation should be 1:3:6. But if it is applied in the car parking area, the ratio will be changed to 1:2:4. Properties of plain cement concrete. Compressive strength: The compressive strength of PCC lies between 200 to …

Quantities of Materials Per Cubic Meter of Concrete Mix ...

🕑 Reading time: 1 minute Quantity of materials such as cement, sand, coarse aggregates and water required per cubic meter of concrete and mortar for different mix proportions varies with the mix design of the concrete and mortar respectively. Following table gives the estimated quantity of materials required per cubic meter of mortar and concrete for various nominal mixes.

Calculation of Cement and Sand Quantity for Plastering

Aug 18, 2020· The mix ratio of plaster mortar is 1:4, So the volumes of materials required would be. Cement required = 1/5 X 0.1524 = 0.03048 cu.m. Sand required = 4/5 X 0.1524 = 0.12192 cu.m. Step-3: Get weights of materials required using densities: To get the weights of materials required in multiply it with its density

How To Calculate Quantities Of Materials For Concrete

Today we will discuss how to calculate quantities of materials for different mix ratio of concrete. (Dry mix method) We will calculate quantities of materials for 1 m3 concrete (By volume). Let us assume the mix proportion is 1 : 2: 4 (cement:sand:stone =a:b:c) Volume of wet concrete = 1 m3. Volume of dry concrete = 1 × 1.54 = 1.54 m3.

Rate analysis for Stone Masonry : | Construction basics re ...

Nov 04, 2020· 1.You shall observe that the rate for Rubble masonry in cement mortar in CM 1 :6 and the rate for plain cement concrete in proportion 1:4:8 are almost equal. 2. The material wastage is a point on which I need to elaborate. As such when we consider the factor 1.52 in the material calculations by dry mix method, we are already considering 2 % ...

Specifications for Plain Cement Concrete (PCC) | Building ...

Sep 05, 2010· 1:2:4 (cement : sand : stone ballast) by volume when specified. Minimum compressive strength of concrete of 1:2:4 proportion shall be 140 kg/cm2 in 7 days. Hand mixing. Mixing shall be done on masonry platform or sheet iron tray. Machine mixing. Stone ballast, sand and cement shall be put into cement concrete mixer to have the required ...

CHAPTER - 3 : PLAIN CONCRETE

IR's Unified Standard Schedule Of Rates 2010 Chapter-3 : Plain Concrete Item No. Description of Item Unit Rate (Rs.) Cement Qty.(qtl.) 032032 in ash pit stones, platform coping stones etc. cum 2339.23 4…

Construction Of 3 00 Km Approximate Temporary Acce Tender ...

Jul 23, 2021· Cum: 18: 3.03: Plain cement concrete 1:4:8 (1 cement: 4 sand: 8 stone aggregate of size 4cm graded downwards) in foundation or elsewhere (excluding the cost of centering/shuttering) as per specifications as directed by Engineer-in-Charge and OC Contract. item10: 377.37: Cum: 19: 3.04

cement consumption in PCC 1:4:8 and M7.5 - Civil Sir

Feb 18, 2020· Ratio of water and cement is known as water cement ratio which is about 45 litre per bag cement for m10 grade of concrete. 1 bag cement required = 45 litre of water. 51 bags = 51×45= 2295 litre of water. So we have required water consumption in pcc 1:4:8 is approx 2295 litre of water for 100m2 having 150 mm thick slab.

PCC Volume Calculator | Free Estimate of Cement, Sand, Jelly

PCC Volume Calculator. Plain Cement Concrete (PCC) is composed mixture of cement, aggregates, sand, water and chemical admixtures. Calculate portland cement concrete or PCC concrete mix design ratio in Cft and determine exactly how much quantity of cement, sand and aggregate is required …

(PDF) CONSUMPTION OF MATERIALS 3.1 Consumptions for ...

(2) That the size of bricks shall be 9 ¾˝ x 4 ¾˝ x 2 ¾˝. (3) Volume of 1 bag (50 Kg) cement = 0.035 m3 TABLE 3.1 – 1: QUANTITIES OF MATERIALS REQUIRED FOR PLASTERING, BRICKWORK, CONCRETING & OTHER ITEMS Sl. Description of items Unit Quantities of materials required. No.

Construction Board: Thumb Rules for Highrise Building to ...

Aug 21, 2019· PCC 1: 4: 8 =3.4 bags/cum 15. PCC 1:5:10 =2.52 bags/cum 16. PCC 1:3:6 =4.2 bags/cum 17. PCC 1:2:4 =6.02 bags/cum ... The use of local aggregates and recycled materials in concrete makes it a 'green' product, which is requested by environmentally responsible owners. ... Session 6 : PCC Work (Plain Cement Concrete) (Free Online Quantity Survey ...

ADDENDUM - 3

177.00 Cum 100-3 Plain Cement Concrete (1:4:8) (cement: fine aggregate: Coarse aggregate) for foundations and under flooring bed using coarse aggregate 40mm size hard, machine crushed granite from approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc.

Rate analysis for PCC 1:4:8 (M7.5) - calculate quantity ...

Aug 09, 2020· Rate Analysis for PCC 1:4:8 :-It is a summary of all the cost involved in doing particular work or unit work like material cost, labour cost, overhead expenses, water charges & contractor profit.For rate analysis, the details about all the operation involved in carrying out the work should be available. The quantities of materials cement sand aggregate and water are required and their cost ...

Rate Analysis of PCC : (Plain Cement Concrete)

Aug 01, 2019· PCC only Labour: Rs.400/Cum. 100 to 150mm thick PCC only Labour: Rs.6.00/Sqft. Plum Concrete Only Labour: Rs.8.50-9.00/Cuft That is 300/Cum. Cement Bag: Rs.50- 60/Bag. Shuttering With Material: Rs.450-550/ Sqm. All above Rates is current market rate and analysis are considered as per Mix design report.